‘Pittsburgh Water broke its promise’
- jmartinez5135
- Jun 30
- 5 min read
District 5 city councilor demands revival of Four Mile Run stormwater project

By Ziggy Edwards and Ray Gerard for Junction Coalition
City Councilor Barb Warwick and her neighbors in The Run are fighting to convince Pittsburgh Water (formerly PWSA) to reverse its unannounced decision to cut the stormwater project from their capital budget. She spearheaded a May 23 press conference in Four Mile Run Field just before making public comments at Pittsburgh Water’s monthly board meeting.
“Pittsburgh Water broke its promise just like everyone in The Run said they were going to do,” she told reporters, referring to predictions by locals since the utility announced its $40+ million project in 2017.
People from The Run have told The Homepage in recent years that they believed work on flood control would only go through if they dropped their opposition to the proposed Mon-Oakland Connector shuttle road. This road was planned to go through their neighborhood and Schenley Park. Residents and allies throughout Pittsburgh eventually defeated the plan when Mayor Ed Gainey canceled it in 2022. Within six months of the project’s demise, Pittsburgh Water removed all green infrastructure elements from their stormwater project.
Green stormwater infrastructure is a set of passive, nature-based solutions to flooding, according to the environmental group PennFuture. It can include manufactured wetlands, swales and rain gardens that collect and hold rainwater before it enters the sewer system, and porous paving that allows water to soak into the ground.
On May 23, Ms. Warwick recalled the November 2022 public meeting where Pittsburgh Water announced these changes. At that time, the water authority reaffirmed its commitment to completing the project, which had been billed as a solution to The Run’s dangerous flooding issues.
“I stood up in front of my neighbors with PWSA CEO Will Pickering, and I said, ‘Don’t worry, guys; they’re going to fix it,’” she told the crowd.
But sometime in 2024, Pittsburgh Water removed all funding for construction of the project from its capital budget.
This choice was only referenced indirectly during Pittsburgh Water’s November 2024 board meeting. Pittsburgh Water board chair Alex Sciulli said the board had earlier met in executive session and discussed “some updates on some projects.” Soon afterward, board member BJ Leber thanked the finance department for a budget-related education session held that week. She referred to “tough decisions in terms of available resources.”
About 25 residents joined Ms. Warwick at the press conference and shared the urgency they felt about the project.
Dana Provenzano owns Zano’s Pub House on Acorn Street in The Run. She talked about flooding that brought water and sewage into the pub, forcing her to close her doors.
“I have to make it safe and sanitary to serve food. No one compensates me for the money I lose when flooding happens,” she said.
Ms. Provenzano called on Pittsburgh Water board members to put themselves in Run residents’ shoes.
“If it was your business, if it was your family, if it was your friends — would you stand up and say, ‘I will reallocate this money to somebody else’?”
“We’re not just talking about a little water in the basement — we’re talking about life-threatening flash floods that blow off manhole covers and fill the streets and homes with sewer water in a matter of minutes,” said Run resident Cynthia Cerrato. “Every time we get a heavy rain my heart freezes, wondering if this is going to be the big one.”
Residents speak up
Immediately after the press conference, Ms. Warwick and three neighbors carpooled to Pittsburgh Water’s offices where the monthly board meeting was being held.
Pastor Mike Holohan is a Run resident and board member of the Greenfield Community Association. He attended the meeting virtually. He said Pittsburgh Water seemed incredulous that Run residents believed the stormwater and Mon-Oakland Connector, or MOC, were linked. When Pittsburgh Water decided to defund the stormwater project, it did not inform the community association ahead of time.
“Pittsburgh Water may give this or that reason for canceling this project. They may say it has nothing to do with the MOC, but when I stop and look at the narrative arc, it seems pretty clear,” he said. “The wealthy people who make things happen don’t see us as a vital neighborhood, but as an obstacle to overcome. They don’t see what I see — that this is an important place where neighbors are friends and children play, and it’s worth protecting.”
Annie Quinn lives in Greenfield and founded the Mon Water Project to advocate for local watersheds.
“This is an environmental injustice happening right here in our neighborhood. It is a human health emergency. We must demand solutions,” she told reporters. “After 10 years and $8.7 million, no physical solution has been installed.”
In her comments to the board, Ms. Quinn challenged them to not only follow through with the scaled-down project Pittsburgh Water promised after the shuttle road project cancellation, but to bring back the original green infrastructure project that included daylighting Four Mile Run stream.
“I request that you go back to your very own studies — that you produced and paid for,” which recommended connecting the stream to the Monongahela River, she said.
She also asked Pittsburgh Water to work with PennDOT during its planned I-376 project above The Run and not allow PennDOT to add runoff from the overpass to the already overburdened water system below.

Pittsburgh Water responds
Mr. Sciulli responded, “We don’t normally comment on the content of our public speakers, but I think it’s important for the record for me to make a few remarks.”
“The Four Mile Run project should have been a crown jewel for green infrastructure, but it met tons of obstacles and challenges to execute the project,” he said.
Mr. Sciulli enumerated some of those obstacles, including the Pennsylvania Department of Environmental Protection adding constraints by reclassifying Panther Hollow Lake as a high-hazard dam.
“The refusal of the railroad company to allow our construction equipment to cross the rail line, even with the use of their own flagmen at outrageous rates, also caused much of the problem,” he added.
Mr. Sciulli responded to concerns about the Mon-Oakland Connector.
“It wasn’t our project,” he said, but as “good public servants” Pittsburgh Water attempted to save taxpayers money by accommodating it and combining construction costs.
Finally, he said PennDOT would not acknowledge its contribution to flooding in The Run and refused to share costs for the stormwater project.
“While this major investment of this project is on pause until we secure the funding, we haven’t stopped trying to solve the problem,” Mr. Sciulli stressed.
That night, former Pittsburgh mayor Bill Peduto responded to media coverage of the press conference in a series of posts to the X social media platform.
“Just a reminder that there was a green stormwater management plan for Four Mile Run. It would have daylighted the streams in Schenley Park, dredged Panther Hollow Lake and ended flooding. Essential Foundation funding ended when the Oakland-Mon Connector project was killed,” the first post read.
Mr. Peduto’s comments contradict Mr. Sciulli’s stated obstacles to the stormwater project and seem to support Run residents’ prediction: No shuttle road, no flood control.
Ms. Quinn held a public meeting in The Run on June 9. About 30 people gathered at Zano’s Pub House to hear an update on the history and status of the stormwater project, as well as discuss next steps to get the funding restored. Read the coverage on Page 5.
Junction Coalition is a grassroots organization comprising residents of Four Mile Run and surrounding communities.
Comments